The Timeline Has Two Halves
Homeowners usually think about construction time — the weeks the crew is in the house. But a remodel timeline has two halves, and the first half happens before demolition: design, decisions, permits, and ordering. Rushing the first half is how projects go sideways. Here is how the whole thing typically unfolds.
Phase 1: Design and Decisions (2–6 Weeks)
We visit, measure, and design the layout with you. You choose cabinets, counters, tile, fixtures, and finishes. This phase takes as long as your decision-making does — some homeowners decide in a week, others need a month of living with samples. There is no wrong pace, but every decision delayed here delays everything after it. We give you a decision checklist with deadlines so nothing stalls.
Phase 2: Permits and Ordering (2–8 Weeks)
These run in parallel. Permit applications go to Prince George's County for electrical, plumbing, and structural work — review times vary with the county's workload. Meanwhile, cabinets and specialty materials are ordered; custom and semi-custom cabinets are built to order and that takes weeks. This is the quiet phase where nothing visible happens but everything important is in motion.
Phase 3: Construction (3–8 Weeks)
Demolition is fast — days. Rough work (electrical, plumbing, structural) follows, then county inspections. Then the visible transformation: drywall, cabinets, countertop templating and installation, tile, flooring, fixtures, paint. A straightforward cabinet-and-counter refresh is on the short end; a full gut with layout changes is on the long end. Weather does not affect indoor work, but material deliveries and inspection scheduling can shift days around.
Where Schedules Actually Slip
Three culprits cause most delays: late decisions (the tile you cannot choose holds up the backsplash, which holds up the final plumbing), unexpected conditions (the rot behind the wall that has to be fixed before proceeding), and change orders (deciding mid-project to move the sink after the plumbing is roughed in). The first is avoidable with the decision checklist. The second is why we investigate before quoting. The third is why we beg you to finalize the design before demolition.
Living Through It
Plan the temporary kitchen before demo day: microwave, toaster oven, coffee maker, a dishwashing station in the laundry room or bathroom. Paper plates for a few weeks are not defeat — they are strategy. We seal the work zone with dust barriers and clean up daily, and we give you a written schedule with the phases so you always know what is happening this week.